S949-105 TD2240 (CCE)
14 Sep 62
Min (3)
COR
Status of Construction
Gap Filler Radar Stations, Various
The status of construction at the various Gap Filler Radar Stations is listed on the attached Appendices "A", "B", "C" and "D". Until detailed reports are received for individual stations, it is impossible to provide the information requested on a complete site-by-site basis. The stations have been grouped according to their approximate overall average but individual percentages for line items will vary. The time required to complete the construction is also an approximate number of months after approval of the DND-8 to DCL. When an individual site is complete will depend on how quickly DCL renegotiates and individual contract and how quickly a contractor resumers construction.
The problem, which we will be confronted with as the result of the derferment of the programme, are as follows:
(RB Whiting) A/C
CCE
2-8702
PS Land acquisition is either completed or nearing completion on all 45 sites.
(RB Whiting) A/C
CCE
APPENDIX "A" to
S949-105 TD2240 (CCE)
dated 14 Sep 62
Sites: Algonquin Park, Belleterre, Elliot Lake, Formosa Relocated, Lac Ste Marie, Nicolet, Scotch Settlement relocated, St Joseph, Timmins, Tobermory
Progress of Construction - 95%
Description of Construction Completed:
Description of work to be Completed:
Time Required to Complete Construction: three (3) months from approved DND-8 to DCL
Status of Contracts: Terminated at above stage of completion